First-generation device

Took the first step toward commercialization
Supporting mid-term objectives

HHMAX-901 parameters are benchmarked against the Helion sixth-generation device. After multiple physical and engineering design iterations, it has completed physical parameter simulations for the entire process of FRC formation-compression and collision fusion. The design was finalized in February 2025, entering the engineering construction phase. Currently, the facility has completed construction and assembly of its entire vacuum system and support structure. It has passed vacuum leak detection and insulation withstand voltage tests, achieving successful plasma ignition in July 2025. This milestone provides robust support for  HHMAX-ENERGY Polyenergy's mid-term development objectives.

Project progress chart
  • 01
    Project initiated in June 2024
  • 02
    Commencement of Physical Master Design in August 2024
  • 03
    October 2024 Base Site Selection
  • 04
    Completion of the physical master plan in November 2024
  • 05
    Commence construction of the launch vehicle by December 2024.
  • 06
    Facility base renovation to commence in February 2025
  • 07
    April 2025 The facility passed the classification application submitted to the Ministry of Ecology and Environment.
  • 08
    June 2025 Completion of the full-scale renovation of the fusion device facility base; Vacuum sealing performance verification of the HHMAX-901 device formation zone passed.
  • 09
    July 2025: HHMAX-901 mainframe construction completed, plasma ignition achieved
  • 010
    Commissioning of the facility will commence in September 2025.